Update v2.0.0.1
This update includes minor changes and bug fixes.
Fixed issue where after using the duration estimation tool, the project refuses to save.
Activities are now added at the end of the Goal list.
Changed wording on Paste menu items.
Actual Start/Finish dates are no longer automatically set when changing Percent Complete if they are already populated.
When a new Activity is created, the Planned Start date is set to the Project Start date or today, whichever is later.
Reserved space for all project component lists on left side (e.g., Stakeholders list), allowing right-click when pasting to an empty list.
Actual Finish date is now automatically populated when Work Status is set to Complete.
On Hold and Canceled statuses cannot be selected for Activities after setting Percent Complete to 100 (Work Status changed to Complete).